The key facts
- Repsol filed five lawsuits in October, seeking about €120 million in compensation
- The defendants are the distributors Iberdrola, Endesa and Naturgy; Red Eléctrica is named as a jointly liable defendant in all cases
- The regulator CNMC previously opened cases into possible violations, including against Repsol itself
Lawsuits against electricity distributors
The Spanish oil and gas company Repsol has filed five lawsuits against electricity distributors, seeking about €120 million in compensation for damage to its industrial facilities during the massive power outage of 28 April 2025, which affected mainland Spain and Portugal. The lawsuits were first reported by El Confidencial, and on Monday Repsol sources confirmed to the newspaper El País that the documents had been filed, Euronews reports.
Who the defendant is for each facility
The lawsuits, filed in October, are directed against the distributors supplying electricity to the affected sites. Repsol is seeking compensation from the distributor Naturgy for the facility in A Coruña, from the distributor Iberdrola for the facilities in Bilbao and Cartagena, and from the distributor Endesa for the facilities in Tarragona and Puertollano. In all five cases, the company is also seeking to hold the grid operator Red Eléctrica jointly liable. Before going to court, Repsol attempted to settle the dispute out of court, but the negotiations yielded no result. Its CEO Josu Jon Imas had already stated in February that the company was preparing a compensation claim.
The investigation into the causes continues
The question of the causes of the blackout and of responsibility remains open. In March 2026, a European group of experts concluded that the outage resulted from a combination of several factors: a rapid rise in voltage and a series of generator disconnections. In April 2026, the Spanish regulator for competition and energy, CNMC, initially opened 20 cases into possible violations of electricity sector rules, and the following week announced new ones. Among the companies named in the first wave of cases are Red Eléctrica, Iberdrola, Endesa, Naturgy and Repsol itself. The regulator said it had found signs of possible violations, but stressed that the blackout had several causes and that the opening of cases does not establish which companies are responsible for it. Thus, Repsol's lawsuits and the CNMC investigation are proceeding in parallel, and a final allocation of responsibility has not yet been made.