The key facts
- Data centers in the Netherlands consumed 5,664 GWh in 2025 — 5% of national consumption, up from 4.6% in 2024
- Consumption grew by 12%, although the number of large centers (about 50) has barely changed in recent years
- In 2024, the Netherlands ranked second in the EU in the share of data centers in electricity consumption, after Ireland (over 21%)
Growing share despite a stable number of facilities
Data centers in the Netherlands consumed 5,664 gigawatt-hours of electricity in 2025, which amounted to 5% of the country's total consumption, up from 4.6% a year earlier. This was reported by the Dutch public broadcasting corporation NOS, citing the Netherlands' statistics agency (CBS). Consumption rose by 12% compared with 2024, while the 2025 figures are preliminary and may be revised.
Who consumes the most
The country has about 200 data centers, of which roughly 50 are large facilities consuming at least 10 GWh per year. It is these that account for more than 90% of the electricity supplied to data centers. Notably, as NOS points out, the number of large centers has remained broadly stable in recent years, yet their consumption has continued to grow — meaning the rising load is due not to an expansion of the facility base but to increased consumption by existing ones.
Position in the EU and data limitations
In 2024, the Netherlands ranked second in the European Union in the share of electricity going to data centers: 4.6% versus 4.2% in Germany. Ireland was the leader, where the figure exceeded 21%. CBS statistics cover only facilities whose core activity is operating data centers and do not include data storage facilities owned by other organizations, including universities and hospitals: their consumption in 2025 is estimated separately at approximately 142 GWh. This means the real total load on the power grid is somewhat higher than the official figure.